Cartmel College accommodation
Until mid-May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the installation of the external district heating pipework at Cartmel College accommodation. From Friday 20 March until September 2026, the contractor will then be working on the connection of the external pipework into plant rooms on the top floor of the houses. Pressure testing and flushing of the pipework will be taking place between Monday 18 May and Friday 5 June.
House 20 Thirlmere
Internal plant room connections: 6 May – 10 September
Services downtime: 20 May
House 46 Bigland
External pipework installation: 16 March – mid-April
Internal plant room connections: 7 April – early May
Core hole: 16 April
Services downtime: 9 July (also affects Houses 47 to 49)
House 52 Haverthwaite
External pipework installation: 30 March – end of April
Internal plant room connections: 14 April – early May
Core hole: 16 April
Services downtime: 6 August (also affects Houses 50 to 51)
House 54 Grange
External pipework installation: 15 April – mid-May
Internal plant room connections: 20 April – mid-May
Services downtime: 11 September (also affects House 53)
House 55 Braystones Tarn
Services downtime: 2 October (also affects House 56)
- Scaffolding will be erected or high-level access machinery will be used at one side of each building. This will allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- The services downtime is expected to take place between 9am and 5pm for a maximum duration of eight hours.
Cartmel family flats and houses
From 7 April until early May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the external district heating pipework to Graduate College - Cartmel family flats and houses. Vital Energi contractors will be installing external pipework only at this time, in readiness for summer internal connections.
Houses 158 – 162 Lyth
External pipework installation: 7 April – mid-April
Houses 163 – 168 Backbarrow
External pipework installation: 13 April – late April
Houses 169 – 171 Hayeswater
External pipework installation: 20 April – early May
Houses 172 – 179 Seathwaite
External pipework installation: 27 April – early May
Encasement work to risers (all spaces): 8 May – early July
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
- Dates can be subject to change.
Between Monday 18 May and Friday 5 June 2026, the Net Zero Energy Project contractor, Vital Energi, will be carrying out pressure testing and flushing of the district heating pipework at Furness accommodation, House 71 Pennington, House 72 Colton, and House 74 Hawkshead.
- Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- Work will progress between 8am – 6pm (Monday to Friday) and is not expected to be noisy. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
- Dates can be subject to change.
Until mid-May 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the external district heating pipework installation works at Graduate College accommodation. From Friday 6 March until mid-May 2026, the contractor will then be working on the connection of the external pipework into plant rooms on the top floor of House 16 Loweswater and House 19 Stickle. Pressure testing and flushing of the pipework will be taking place between Monday 18 May and Friday 5 June.
House 7 Crummock Water
External pipework installation: 27 April – early May
House 8 Derwentwater
External pipework installation: 5 May – early May
Core hole: 6 May
Internal pipework installation: 6 May
House 9 Devoke
External pipework installation: 5 May – mid-May
Core hole: 6-12 May
Internal pipework installation: 6 May – mid-May
House 11 Ennerdale
External pipework installation: 20 April – early May
Core hole: 20 April
Internal pipework installation: 20 April
House 16 Loweswater
Internal plant room connections: 27 March – end of April
Services downtime: 26 August (also affects Houses 12 to 15)
House 19 Stickle
Internal plant room connections: 7 April – mid-May
Services downtime: 12 May (also affects Houses 17 and 18)
- Scaffolding will be erected or high-level access machinery will be used to allow the installation of pipework up the outside of the buildings and into plant rooms.
- Some pedestrian access routes in the local area will be closed. Diversion signage will be in place and building entrances will be maintained at all times.
- Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- The services downtime is expected to take place between 9am and 5pm for a maximum duration of eight hours.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
- Dates can be subject to change.
Between Monday 18 May and Friday 5 June 2026, the Net Zero Energy Project contractor, Vital Energi, will be carrying out pressure testing and flushing of the district heating pipework at Grizedale College accommodation, House 30 Easdale Tarn.
- Vital Energi contractors will be accessing the communal stairwells but won't need access to any student flats.
- On Monday 5 October 2026, there will be a services downtime. The downtime is expected to take place between 9am-5pm for a maximum of eight hours. This will also affect services in House 31 Longber, Graduate College.
- Work will progress between 8am – 6pm (Monday to Friday) and is not expected to be noisy. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
- Dates can be subject to change.
Until July 2026, the Net Zero Energy Project contractor, Vital Energi, will be working on the connection of the external district heating pipework into plant rooms at Lonsdale College accommodation. Pressure testing and flushing of the pipework will be taking place between Monday 18 May and Friday 5 June.
House 32 Cantsfield
House 34 Whittington
Services downtime: 16 July
House 35 Beckfoot
House 36 Tunstall
Internal plant room connections: 13 May – early July
Services downtime: 4 June
House 37 Wennington
House 39 Barbon
Services downtime: 29 July
House 40 Casterton
Services downtime: 30 July (also affects Houses 41 and 42)
House 43 Arkholme
Internal plant room connections: 7 April – early May
Services downtime: 27 August (also affects Houses 44 and 45)
- Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- The services downtime is expected to take place between 9am and 5pm for a maximum duration of eight hours.
- Work will progress between 8am – 6pm (Monday to Friday) and will be noisy at times. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
- Dates can be subject to change.
Between Monday 18 May and Friday 5 June 2026, the Net Zero Energy Project contractor, Vital Energi, will be carrying out pressure testing and flushing of the district heating pipework at Pendle College accommodation.
House 21 Ullswater
Services downtime: 18 June (also affects Houses 22 and 23)
House 24 Winewall
Services downtime: 2 July (also affects Houses 25 and 26)
House 27 Crowtrees
Services downtime: 6 August (also affects House 28)
House 29 Barnoldswick
- Vital Energi contractors will be accessing the communal stairwells but won’t need access to any student flats.
- The services downtime is expected to take place between 9am and 5pm for a maximum duration of eight hours.
- Work will progress between 8am – 6pm (Monday to Friday) and is not expected to be noisy. The project webpages list alternative study spaces if required.
- If any other localised work is scheduled that may impact you, your Accommodation Manager will be in contact. If you need any further information in the meantime, please get in touch with them.
- Dates can be subject to change.